ROOQ ELECTRIC successfully completed the 18*4MVA power distribution project in Zhambyl, Kazakhstan

ROOQ ELECTRIC GROUP CO., LTD has recently successfully completed the 18*4MVA power distribution project in the Jiangbuer region of Kazakhstan and put it into operation smoothly. The successful completion of this project not only demonstrates the professional strength of ROOQ Electric Group, but also provides a solid guarantee for the local power supply.

Project Background

The Jiangbuer region is located in the south of Kazakhstan and is an important economic and industrial center. With the rapid development of the economy, the demand for electricity is also increasing. In order to meet the growing local power demand, ROOQ Electric Group has undertaken the construction task of the Jiangbuer 18*4MVA power distribution project.

Project Details

The project includes 18 4MVA transformer groups, each of which uses the latest technology and equipment to ensure efficient and stable power transmission. The main work of the project includes the installation of transformers, the construction of distribution lines, and the improvement of related supporting facilities. The entire project is carried out under strict quality control and safety management to ensure the high standards and high quality of the project.

Project Implementation

ROOQ Electrical Group’s engineering team overcame various difficulties, including adverse weather conditions and a complex construction environment, and completed all tasks of the project on time through careful planning and execution. During the project implementation, ROOQ Electrical Group adopted advanced construction technology and management methods to ensure the smooth progress of the project.

Project Significance

The successful operation of the Zhambyl 18*4MVA power distribution project not only improves the local power supply capacity, but also provides strong support for local economic development. The completion of this project marks another major breakthrough for ROOQ Electric Group in the field of international power engineering, and further consolidates the company’s leading position in the international market.

Customer Feedback

After the completion of the project, ROOQ Electric Group received high praise from customers in Kazakhstan. The customer said that the professionalism and efficient execution shown by ROOQ Electric Group during the implementation of the project were impressive, and hoped to have more cooperation opportunities in the future.

ROOQ Electric Group will continue to uphold the concept of “quality first, customer first”, continuously improve its technical level and service capabilities, and provide more high-quality power solutions for global customers. The successful implementation of the Zhambyl project has laid a solid foundation for the company’s future expansion in the Central Asian market.